SNAGGING · DEFECT LANGUAGE
Near completion, the architect walks the building and writes a snagging list (US:
punch list) of defects to fix. The language is short and factual:
rub down and repaint.
No blame, no adjectives of mood — just what's wrong and what fixes it.
Item 1 — Entrance, glass door: handle scratched; replace. Item 2 — Reception, north wall: paint finish uneven, visible roller marks; rub down and apply one further coat. Item 3 — WC 1: tile grout missing along the skirting; make good. Item 4 — Corridor: skirting board not aligned at the junction; refix level. Each item is closed only when re-inspected and signed off.
What is the defect on the reception north wall?
A snag is closed as soon as it's written down.
Give the one-word defect term used for the WC grout: it is along the skirting.